Ivanhoe cuts Kamoa-Kakula’s 2027 copper guidance by a fifth

Ivanhoe has cut 2027 guidance at Congo's Kamoa-Kakula to 300,000 to 350,000 tonnes of copper and lowered its steady-state outlook. Costs are rising too.

Ivanhoe cuts Kamoa-Kakula's 2027 copper guidance by a fifth

Ivanhoe Mines has cut its 2027 production guidance for Kamoa-Kakula, the giant copper complex in the Democratic Republic of Congo, by 19%. The mine is now expected to produce 300,000 to 350,000 tonnes of saleable copper next year, down from 380,000 to 420,000 tonnes, The Northern Miner reported.

Ivanhoe also lowered the mine’s long-term outlook. The three existing concentrators are now expected to produce 400,000 to 450,000 tonnes a year at steady state, down from more than 500,000.

What went wrong

Recovery from seismic activity and flooding in May 2025 is taking longer than expected. Mining on Kakula’s eastern side will now start in late first-quarter 2028 rather than the fourth quarter of 2027, and drilling and engineering studies have lowered the maximum mining rate at Kakula.

Costs are rising as well. Ivanhoe raised its 2027 cash cost guidance to $2.50 to $3.00 a pound, from $2.10 to $2.50, citing higher diesel prices, lower grades and lower output.

The recovery plan

  • Open pits: waste stripping at shallow Kamoa deposits begins in the first quarter of 2027, with first ore in the third quarter.
  • A fourth concentrator: targeting about 500,000 tonnes a year, it moves into detailed engineering from early 2027 and would take 18 to 24 months to build after approval.
  • Spending: the 2027 budget is $950 million to $1.2 billion, plus $100 million to $200 million for open-pit stripping.
  • Next update: an updated life-of-mine plan is due in March 2027.

Why it matters

Kamoa-Kakula is one of the most important new sources of copper in the world, and forecasts of future supply lean heavily on it. A lower ceiling at one of the best new mines adds to evidence that copper supply growth will lag demand from grids and electrification.

Investors reacted sharply. Ivanhoe shares fell as much as 14% in Toronto on November 4 to their lowest since July 2022, and TD Cowen cut its rating to hold. The March life-of-mine plan will show whether the new numbers are a floor.

Daniel Osei-Bonsu